Breagh
- Type: Rig
- field
- Latitude: 54.6013303
- Longitude: 0.4886370
Breagh Gas Field Profile
Location and Geology
The Breagh gas field is situated in the Southern North Sea, approximately 65 km north-east of the UK coast. It is located in blocks 42/13a and 42/12a at a water depth of about 62 metres (or 194 feet).
The field is a conventional Carboniferous reservoir, indicating it is based on geological formations from the Carboniferous period.
Discovery and History
The Breagh field was discovered in July 1997 by the discovery well 42/13-2, which encountered a 121m gas column. An earlier well, 42/13-1, drilled by BP in 1968, was declared commercially non-viable.
Key milestones include:
- 2009: RWE Dea acquired a 70% stake in the field.
- 2010: Heerema was awarded the contract for the construction of the jacket, topsides, and piles.
- 2011: Government approval was granted, and the Breagh A platform was successfully installed.
- 2013: First gas production began.
- 2015: INEOS announced the acquisition of RWE Dea's share in the field.
Field Development
The Breagh field is being developed in two phases:
Phase One:
- Development began in 2011.
- The Breagh A platform, a normally unmanned installation (NUI), was installed at the west side of the field in October 2011.
- Eight production wells were drilled from the platform.
- Gas is exported through an offshore pipeline to Cotham Sands, Redcar, and then via a 10km onshore pipeline to the Teesside Gas Processing Plant (TGPP) for further processing and delivery into the UK National Transmission System.
Phase Two:
- Approved by the UK Department of Energy and Climate Change (DECC) in July 2011.
- This phase involves the installation of another NUI, Breagh Bravo, at the east end of the field.
- Additional wells will be drilled from the new platform and tied back to Breagh Alpha.
Infrastructure and Operations
Breagh A Platform:
- The platform features a 85m-tall jacket supported by piles weighing 4,000t, with topsides weighing 1,400t.
- It includes a 10t diesel crane, a helideck, 12 well slots, a gas production manifold, and seven risers.
- The platform has overnight accommodation for 12 people.
Subsea System:
- The subsea production systems include dry Christmas-trees, production piping, and a production manifold.
- Gas and fluids flow from the Christmas-trees through the flow lines to the manifold and then to the onshore processing facility via the export riser.
Processing and Transmission:
- The Teesside Gas Processing Plant (TGPP) at Seal Sands has a capacity to process 11.3 million cubic metres of natural gas per day and can meet up to 10% of the UK’s gas demand.
Ownership and Partners
- The field is currently operated by INEOS with a 70% interest.
- Sterling Resources owns the remaining 30% interest.
Production
- First gas from the field was achieved in October 2013 with a total flow rate of 2.75 million cubic metres of gas per day.
- The field currently produces at an annual rate of 1.1 billion cubic metres of gas during phase one.
- Recent developments include the start-up of a new onshore electric-drive compressor at TGPP, which will increase gas flows with a lower carbon footprint.
Environmental and Technological Advancements
- The field is noted for having one of the lowest carbon intensities of gas fields in the UK.
- The introduction of an electric-driven compressor at TGPP aims to reduce the carbon footprint of gas production.
Contracts and Contractors
- Key contractors include Heerema for the construction of the jacket, topsides, and piles; Allseas for the engineering, installation, and pre-commissioning of the offshore pipeline and fibre-optic cable; and AMEC for modifying and extending the gas processing plant.
Development Costs
The Breagh field development is estimated to have cost approximately £1 billion.