Mamba
- Type: Rig
- complex
- Latitude: -10.8753000
- Longitude: 41.2086000
Location and Geology
- The Mamba gas fields are situated in the ultra-deep waters of the Mozambique Channel, specifically within Block Area 4.
- The water depths vary, with the Mamba Northeast field located at approximately 6,540 feet (1,998 meters), the Mamba North 1 discovery at 1,690 meters, and the Mamba North East 1 at 1,848 meters.
Discovery and History
- The discoveries in the Mamba area began in 2011 with the Mamba South discovery, followed by the successful drilling of the Mamba North 1 prospect in 2012.
- Further discoveries and appraisals have been conducted since then, with significant gas reserves identified.
Field Details
Mamba Northeast
- Operator: Mozambique Rovuma Venture
- Ownership: China National Petroleum, Empresa Nacional de Hidrocarbonetos EP, Eni, Exxon Mobil, Galp Energia SGPS, and Korea Gas.
- Production Start: Expected to begin in 2028, with peak production forecasted in 2040 and continuing until the economic limit is reached in 2078.
- Reserves: Part of the larger Mamba Complex, with estimated reserves of 75 trillion cubic feet (tcf) of gas in place for the entire complex.
Mamba North
- Operator: Eni S.P.A
- Ownership: Eni S.P.A. (25%), ExxonMobil (25%), Empresa Nacional de Hidrocarbonetos de Mozambique (20%), and other partners (30%).
- Status: Operating
- Reserves: Estimated gas reserves of approximately 424.7 million cubic meters (as of 2018) and additional resources.
Mamba Complex
- Operator: Mozambique Rovuma Venture
- Ownership: Similar to Mamba Northeast, with China National Petroleum, Empresa Nacional de Hidrocarbonetos EP, Eni, Exxon Mobil, Galp Energia SGPS, and Korea Gas involved.
- Production Start: Expected to begin in 2028, with peak production forecasted in 2029 and continuing until the economic limit is reached in 2057.
- Development: The project involves the drilling of approximately 24 wells, along with subsea manifold and subsea trees. The development cost is estimated at $23 billion.
Contractors and Partners
- Key contractors involved in the Mamba projects include The ERM Group, Impacto, and Projectos e Estudos Ambientais.
Production and Reserves
- The Mamba Complex, which includes Mamba Northeast and Mamba North, is estimated to have around 75 tcf of gas in place.
- Production from the Mamba Northeast is expected to start in 2028 and peak in 2040, while the Mamba Complex production is expected to start in 2028 and peak in 2029.
Project Timeline
- Final Investment Decision (FID): Expected in 2025 for both Mamba Northeast and the broader Mamba Complex.
- Production Start: 2028 for both projects.
Economic and Operational Data
- The development of the Mamba Complex is expected to involve significant capital expenditure, with an estimated $23 billion for the project.
- Production will continue until the fields reach their economic limits, with the Mamba Northeast expected to continue until 2078 and the Mamba Complex until 2057.