BARD Offshore 1

  • Type: Wind Farm
  • Latitude: 54.3550000
  • Longitude: 5.9810000

General Information

  • Name: BARD Offshore 1 (BO1)
  • Location: North Sea, approximately 100 km northwest of Borkum Island, Germany.
  • Water Depth: The wind farm is situated in waters with depths ranging from 40 to 44 meters.

Ownership and Operation

  • Current Owner: Ocean Breeze Energy, which is owned by funds managed by Macquarie Asset Management (MAM).
  • Operator: Ocean Breeze Energy GmbH.

Capacity and Turbines

  • Total Capacity: 400 MW.
  • Number of Turbines: 80 BARD 5.0 wind turbines, each with a rated capacity of 5 MW.
  • Turbine Specifications:
    • Rotor diameter: 122 meters
    • Hub height: 90 meters above water level
    • Total height of the structure: 152 meters
    • Three-bladed rotor with electronic pitch system and a three-level gearbox and six-pin double-fed asynchronous generator.

Foundation and Installation

  • Foundation Type: Tripile foundations, consisting of three pylons connected by a transition piece. Each pylon weighs 72 tons, and the foundation structure weighs 239 tons in total.
  • Installation: The turbines were installed using jack-up barges such as Windlift, JB 115, JB 117, and Thor. The crews were transported and provided offshore access by the Amplemann system on the VOS Sympathy vessel.

Grid Connection

  • Grid Connection: The power generated is transmitted to the Borwin I (Alpha) Offshore platform, where it is converted into high-voltage direct current (HVDC) before being transmitted to the German power grid through a 200 km cable line. The power is then fed into the 380 kV German national grid.

Environmental Impact

  • Energy Production: The wind farm produces approximately 1.6 billion kWh of electricity per year, enough to power around 430,000 to 463,000 households.
  • CO2 Reduction: It is expected to reduce CO2 emissions by about 452,061 tons annually.

Construction and Timeline

  • Construction Start: March 2010.
  • First Power Input: December 2010.
  • Commissioning: Officially inaugurated on August 26, 2013, although it faced several delays and was fully operational later.
  • Challenges: The project faced significant delays, cost overruns (initially estimated at over €1 billion but eventually costing around €3 billion), and technical issues, including overvoltage and harmonics problems. There were also fatalities during construction.

Financial and Funding

  • Investment: The project involved a total investment of more than €1 billion.
  • Funding: Supported by a €53.1 million grant from the European Energy Programme for Recovery (EEPR) initiative by the European Commission.

Contractors and Suppliers

  • Turbine Supplier: BARD Engineering developed and supplied the turbines.
  • Foundation Structures: Cuxhaven Steel Construction produced the foundation structures.
  • Rotor Blades: SGL Rotec supplied the rotor blades.
  • Offshore Access: Ampelmann provided the platforms for offshore access.
  • Cable Installation: ABB installed the sea and land cables, and NSW delivered the submarine and offshore cables.
  • Transmission Link: TenneT and ABB were involved in building the transmission link to the German grid.

Maintenance and Operation

  • O&M Contractor: Offshore Wind Solutions (OWS) has been responsible for the operation and maintenance since 2014.
  • Logistical Support: Acta Auriga, an Ulstein-designed service operation vessel, was contracted for logistical support starting in January 2018.

Power Purchase Agreement

  • Power Purchase: RWE Supply and Trading signed a long-term green purchase agreement to market the electricity from BARD Offshore 1 until 2030. The wind farm's electricity will also be used in RWE-developed electrolyser projects to produce green hydrogen starting in 2026.
Flag Name Type Date
BREEZE ENABLER baycraft 11/3/2024
BREEZE ENABLER baycraft 9/19/2024
BREEZE ENABLER baycraft 8/28/2024
BREEZE ENABLER baycraft 8/27/2024
BREEZE ENABLER baycraft 8/13/2024
BREEZE ENABLER baycraft 8/12/2024
BREEZE ENABLER baycraft 8/12/2024
BREEZE ENABLER baycraft 8/12/2024
BREEZE ENABLER baycraft 8/5/2024
BREEZE ENABLER baycraft 7/30/2024
Accept Reject