Dafeng H5

  • Type: Wind Farm
  • Latitude: 33.5170000
  • Longitude: 121.3750000

Project Name

Jiangsu Dafeng H5 Offshore Wind Farm

Location

The project is located in the Yellow Sea, Jiangsu, China.

Developer and Operator

The project was developed by Yancheng Guofeng Offshore Wind Power.

Capacity and Electricity Generation

  • The wind farm has a total nameplate capacity of 206.4 MW.
  • It generates approximately 610,000 MWh of electricity per year.

Turbines and Foundations

  • The project uses 32 wind turbines supplied by Goldwind Science & Technology, each with a 6.45 MW nameplate capacity.
  • The wind turbines are installed on fixed foundations, specifically using an array of monopile foundations.

Construction and Operational Status

  • The construction of the project commenced in 2020.
  • The wind farm entered into commercial operation in December 2021 and is currently active.

Environmental Impact

  • The project contributes to reducing carbon dioxide emissions and generates clean energy, although specific emissions reduction figures for this project are not provided in the sources.

Contractors Involved

  • Goldwind Science & Technology Co Ltd was selected as the turbine supplier for the project.
Accept Reject