Formosa 1 OWF Phase 1

  • Type: Wind Farm
  • Latitude: 24.6920000
  • Longitude: 120.8110000

General Information

  • Name: Formosa 1 Offshore Wind Farm
  • Location: Approximately 6 km offshore of Miaoli County in the Taiwan Straits.
  • Country: Taiwan
  • County/Zone: Offshore Miaoli County

Phase 1 Details

  • Commissioning Date: April 2017.
  • Number of Turbines: 2 wind turbines.
  • Turbine Model: Siemens SWT-4.0-120.
    • Rated Capacity: 4 MW each.
    • Rotor Diameter: 120 meters.
    • Rotor Blade Length: 58.5 meters.
    • Swept Area: 11,300 square meters.

Technical Specifications

  • Total Installed Capacity: 8 MW.
  • Foundation Type: Monopile foundations.

Operational Details

  • Commercial Operation Start: April 2017.
  • Monitoring and Maintenance: The wind turbine performance is constantly monitored from Brande, Denmark by Siemens.

Developers and Owners

  • Developer: Swancor Renewable Energy.
  • Operators: Swancor Renewable Energy.
  • Owners: Jointly owned by Ørsted (35%), JERA Co. (32.5%), Macquarie Capital (25%), and Swancor (7%).

Financial and Regulatory

  • Power Purchase Agreement: The power generated is distributed to Taiwan Power Company based on a feed-in tariff agreed in a 20-year power purchase agreement.
  • Investment and Funding: The project was supported by a memorandum of understanding signed in March 2017, with funding secured from local and international banks in June 2018.

Environmental Impact

  • Power Generation: The first phase is capable of supplying clean electricity to a portion of the total 128,000 households that the entire Formosa 1 project aims to support.

This phase served as a demonstration project, marking the beginning of Taiwan's venture into offshore wind energy and paving the way for the larger second phase of the Formosa 1 Offshore Wind Farm.