Formosa 1 OWF Phase 1
- Type: Wind Farm
- Latitude: 24.6920000
- Longitude: 120.8110000
General Information
- Name: Formosa 1 Offshore Wind Farm
- Location: Approximately 6 km offshore of Miaoli County in the Taiwan Straits.
- Country: Taiwan
- County/Zone: Offshore Miaoli County
Phase 1 Details
- Commissioning Date: April 2017.
- Number of Turbines: 2 wind turbines.
- Turbine Model: Siemens SWT-4.0-120.
- Rated Capacity: 4 MW each.
- Rotor Diameter: 120 meters.
- Rotor Blade Length: 58.5 meters.
- Swept Area: 11,300 square meters.
Technical Specifications
- Total Installed Capacity: 8 MW.
- Foundation Type: Monopile foundations.
Operational Details
- Commercial Operation Start: April 2017.
- Monitoring and Maintenance: The wind turbine performance is constantly monitored from Brande, Denmark by Siemens.
Developers and Owners
- Developer: Swancor Renewable Energy.
- Operators: Swancor Renewable Energy.
- Owners: Jointly owned by Ørsted (35%), JERA Co. (32.5%), Macquarie Capital (25%), and Swancor (7%).
Financial and Regulatory
- Power Purchase Agreement: The power generated is distributed to Taiwan Power Company based on a feed-in tariff agreed in a 20-year power purchase agreement.
- Investment and Funding: The project was supported by a memorandum of understanding signed in March 2017, with funding secured from local and international banks in June 2018.
Environmental Impact
- Power Generation: The first phase is capable of supplying clean electricity to a portion of the total 128,000 households that the entire Formosa 1 project aims to support.
This phase served as a demonstration project, marking the beginning of Taiwan's venture into offshore wind energy and paving the way for the larger second phase of the Formosa 1 Offshore Wind Farm.