  • Location: The Noshiro Port Offshore Wind Farm is situated in the Sea of Japan (East Sea), off the coast of Akita Prefecture, Japan.

Development and Ownership

  • Developer: The project was developed by Akita Offshore Wind Corporation (AOW), a special purpose company established jointly by several partners including Marubeni Corporation, Obayashi Corporation, Tohoku Electric Power Co., Inc., Cosmo Eco Power Co., Ltd., The Kansai Electric Power Co., Inc., Chubu Electric Power Co., Inc., and others.
  • Ownership: The project is co-owned by multiple companies, each holding a 10% stake. These include Akimoku Steel Casting, Chubu Electric Power, Cosmo Eco Power, Kanpu, Kato Construction, Kyouwa Oil, Marubeni, Obayashi, The Kansai Electric Power, and Tohoku Sustainable & Renewable Energy.

Technical Details

  • Turbines: The wind farm features 20 Vestas V117-4.2 MW wind turbines, each with a nameplate capacity of 4.2 MW. These turbines have a rotor diameter of 117 meters and are installed on fixed foundations using monopile structures.
  • Total Nominal Power: The total nominal power of the Noshiro Port Offshore Wind Farm is 84 MW (uprated turbines).
  • Hub Height: Specific details on the hub height are not provided in the sources.

Construction and Operation

  • Construction Start: The construction of the project began in February 2021.
  • Commercial Operation: The Noshiro Port Offshore Wind Farm started commercial operation on December 22, 2022, based on the feed-in tariff program for renewable energy (FIT).
  • Operation and Maintenance: Vestas Offshore Wind is the O&M contractor for the project for a period of 20 years. Akita Offshore Wind Corporation plans to operate and maintain the wind farm for 20 years, with its basis located at Noshiro Port.

Power Purchase Agreement

  • Off-taker: The power generated from the project is sold to Tohoku Electric Power under a power purchase agreement (PPA) at a rate of $0.332/kWh for a period of 20 years. The contracted capacity is 84 MW.

Impact and Capacity

  • Energy Supply: The Noshiro Port Offshore Wind Farm supplies enough clean energy to power approximately 75,308 households.

Financial and Project Details

  • Project Cost: The overall project cost for both Akita Port and Noshiro Port wind farms is approximately 100 billion Japanese Yen (around $746 million).