Nyuzen
- Type: Wind Farm
- Latitude: 36.9680000
- Longitude: 137.4720000
General Information
- Wind Farm Name: Nyuzen
- Country: Japan
- Location: Offshore from Nyuzen-machi, Shimoniikawa-gun, Toyama Prefecture.
Developer and Ownership
- Developer: Nyuzen Marine Wind LLC.
- Owner: VENTI JAPAN Inc..
Operational Details
- Commissioning Date: The project was officially operational as of October 17, 2023, with a project completion ceremony held on this date.
- Operator: Mitsui (for the wind farm), and Chubu Electric Power Co., Inc. (for offshore transmission).
Turbines and Capacity
- Number of Turbines: 3 units
- Turbine Model: Guangdong Mingyang MYSE3.0/135
- Power per Turbine: 3,000 kW (each turbine is rated at 3 MW)
- Total Nominal Power: 7,495 kW (downrated turbines).
Physical Location
- Latitude: 36° 57' 36.4"
- Longitude: 137° 30' 33"
- Depth: -15 meters
- Distance from Shore: Approximately 2 kilometers.
Environmental Impact
- CO2 Reduction: Approximately 10,100 tons of CO2 per year.
- Equivalent Demand of Households: The wind farm will provide renewable power to approximately 3,600 local households annually.
Construction and Installation
- Construction Vessel: The wind turbines were installed using Shimizu’s jack-up vessel, “BLUE WIND”.
- Start of Operations: The wind farm began full operations in October 2023, with an expected power sales period of 20 years.
Power Purchase Agreement
- Power Purchaser: Hokuriku Electric Power Company.
Flag | Name | Type | Date |
---|---|---|---|